Project Info
- Client : Saudi Aramco/Sumitomo Chemicals
- Rabigh Project Site 02 : Common Utilities/Tank Farm Pkgs@ PetroRabigh
- Main Contractor : Petrofac
- Status : UO2/UO3 Pkg's Handed Over & UO4 Pkg Ongoing (Progress 87.3% as of 4th August)
Project Details
Earthworks and Under/Above Ground Civil Works
More Project Details
Scope of Work: Earthworks and Under/Above Ground Civil Works as follow;
- Site Preparation & Temporary Facilities including HCIS Fences
- Waste & Sewage Water Plant Complete Package including coating/painting
- SS Buildings include all finishes and plumbing works x 3 (Pre-cast+Cip)
- Tanks foundations including Dyke Walls/Ditches/HDPE/Marl Paving x 5
- Pipe Sleepers and different kind of supports/foundations
- Underground Pipe & Cable Trenches including SYS/RTR pipe laying 2” to 24”
- Asphalt Roads, Markings & Concrete Paving’s